Independent Expert Review of the Pak Beng Dam EIA
International Rivers commissioned four experts to review project documents for the Pak Beng Dam in order to better understand the...
Independent Review of Don Sahong Dam EIA
A technical review of the Don Sahong Dam’s 2013 Environmental Impact Assessment (EIA) reveals critical knowledge gaps and inaccuracies, which...
Independent Expert Review of the Myitsone Dam EIA
A survey of the “Environmental Impact Report of Hydropower Development in the Upper Reaches of the Ayeyawady River” has found...
A 2007 Review of the Don Sahong Dam's Environmental Impact Assessment (EIA) Report
A 2007 Review of the Don Sahong Dam’s Environmental Impact Assessment (EIA) report carried out by the Mekong River Commission...
Technical Review of the Xayaburi Environmental Impact Assessment
In April 2011, five international Mekong specialists carried out a critical analysis of the Xayaburi Dam Environmental Impact Assessment (EIA)....
Third Suspension for HidroAysén Environmental Review
” target=”_blank”>International Rivers Patagonia campaign. There is nothing like having a child to make one remember the importance of having...
Independent Review Highlights the True Costs of Belo Monte Dam
The true costs of the Belo Monte Hydroelectric Project, planned for the Xingu River in the Brazilian Amazon, have...
RIMA Hidrelétrica Belo Monte
Veja o Relatório de Impacto Ambiental da hidrelétrica Belo Monte
Review of Environmental Impact Assessment for Theun-Hinboun Expansion Project
This review of the August 2007 drafts of the Environmental Impact Assessment (EIA) and Environmental Management and Monitoring Plan for...
IRN technical review of Mekong Secretariat 1994 Mekong mainstream dam plan
This technical review of the Mekong Secretariat’s “Mekong Mainstream Run of River Hydropower” report, dated 1994, identifies serious shortcomings of...